Modern buried county command post built in 1998 and upgraded in 2014 for about 60 staff, with redundant power, water, filtered air, resilient communications and radio studio.
Floor Area · reported
Start date not established
Published date and precision preserved
Unit-attributed from its source article
Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware.
Provisional audited central concept screen; expected-risk calibration is pending. It is not yet a risk-adjusted expected cost.
Method, scope and confidence →6 photographs sourced from the original article, with captions where available.
Published, calculated and proxy dimensions are deliberately separated. Missing evidence stays visible instead of becoming zero.
Rock in place removed before bulking; the excavation-pricing quantity.
Internal airspace; not the amount of rock removed.
Blasted material after bulking; the haul and disposal quantity.
These cubic metres are not interchangeable.
Usable, floor or footprint area; the label is preserved because these are not always interchangeable.
Floor Area · reported · Publisher articleRock in place removed before bulking; the quantity used to price excavation.
12% of structural scope as a buried-class screen · Audit revisionInternal air or chamber volume. It is not solid excavation without overbreak, access and support geometry.
No usable quantity in the reviewed source · Evidence gapBlasted material after bulking, or its handled mass. No swollen cubic metres are inferred when only tonnes are modelled.
No rock mass-handling scope applies to the audited morphology. · Audited morphologyLength alone is insufficient; a costable tunnel also needs width, height or cross-sectional area.
No tunnel geometry applies to the audited morphology. · Audited morphologyPublished chamber or arch geometry used to test volume and support assumptions.
No usable quantity in the reviewed source · Evidence gapRock surface requiring bolts, mesh or shotcrete, preferably measured in square metres.
Rock-support surface does not apply to this audited morphology. · Audited morphologyCounts and dimensions of access, transfer, utility and emergency interfaces.
Archetype portal/escape count. · Reviewed base modelCast inner structures and linings, kept separate from excavated rock and reinforcement mass.
Reported facility floor/shelter area is used as the screening usable-area basis. Archetype concrete factor is 2 m³ per usable m². · Reviewed base modelGroundwater, inflow, drainage, pumping and moisture-control evidence affecting construction and operation.
Water · Publisher articleThe headline answers the current replacement question. Historic cost, CPI and construction-index comparisons remain separate because they answer different questions.
Different specifications receive different estimates; they are not used as the upper and lower limits of one answer.
Preserves documented capacity, protection, autonomy and redundancy using current construction methods.
Requires a modern structural, fire, protection and supplier performance brief.
Requires IT load, cooling topology, grid capacity, redundancy and autonomy. Server hardware is excluded.
No representative facility construction cost selected
General purchasing-power comparison—not a construction quote
Broad BKI proxy—not a bunker-specific rebuild price
Scope lock. Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware. The article describes one anonymous modern underground concrete county command post built in 1998, one of fifteen similar facilities built nationally during the 1990s, and comprehensively renovated in 2014. About 60 people can work there. It is intended to su…
Audit revision sweden-replacement-audit-2026.08.15. The central WBS below incorporates the 61-article review. The former deterministic low/base/high cases remain available only as sensitivities and revision history.
Direct works + owner / design / investigation + legacy concept contingency
Central quantities × current installed-rate screen.
Not yet probability-weighted. The current legacy concept contingency remains separate.
22% applied to the direct-work screen.
Raw model SEK 88.9m · rounded for Confidence D.
Transitional limitation. SEK 15,118,500 is still a blanket concept contingency, not probability-weighted expected risk. This is why the amount is labelled provisional. The audited command buried WBS remains the central scope ledger.
Two source articles are merged into one physical facility record.
61/100 article-geometry completeness. Detailed source extraction is available in the original-article audit.
Confidence D · geometry completeness 61/100
Largest active lines in the audited central component schedule.
The workbook publishes one revised central schedule. Its prior low and high stress cases are retained only under sensitivities; no line-level probability distributions are implied.
Excavation, temporary works, waterproofing and backfill · SEK 1,008,000
Drainage, sumps and moisture control · SEK 336,000
Integrated testing, commissioning and public-safe documentation · SEK 1,950,000
| Change | Scope | Audited base | Quantity / rate basis | Provenance |
|---|---|---|---|---|
| Retained | 03High-mass reinforced-concrete shellStructural | SEK 8,400,000 | 1,200 m³ × SEK 7,000 / m³Derived From Published quantity · Assumption rateReported facility floor/shelter area is used as the screening usable-area basis. Archetype concrete factor is 2 m³ per usable m². | Existing archive WBS |
| Retained | 04Installed reinforcementStructural | SEK 3,780,000 | 108,000 Kg × SEK 35 / KgDerived From Published quantity · Assumption rateReported facility floor/shelter area is used as the screening usable-area basis. Archetype concrete factor is 2 m³ per usable m². Archetype reinforcement intensity is 90 kg per concrete m³. | Existing archive WBS |
| Retained | 05Interior construction and conventional MEPBuilding Services | SEK 27,000,000 | 600 m² / 6,458 ft² × SEK 45,000 / Usable m²Derived From Published quantity · Assumption rateReported facility floor/shelter area is used as the screening usable-area basis. Fit-out factor is 1 times the reference scale. | Existing archive WBS |
| Retained | 06Protection, resilience and standby systemsProtection | SEK 12,000,000 | 0.67 Project × SEK 18,000,000 / ProjectAssumption quantity · Assumption rateOne protection package per 900 usable m² / 9,688 ft², subject to a 0.5-package minimum. | Existing archive WBS |
| Retained | 07Buried access, escape and utility interfacesSite And Access | SEK 6,000,000 | 1 Project × SEK 6,000,000 / ProjectAssumption quantity · Assumption rateArchetype portal/escape count. | Existing archive WBS |
| Added | R243Excavation, temporary works, waterproofing and backfill | SEK 1,008,000 | 12% of structural scope as a buried-class screen | Class assumption — earthworks take-off required |
| Added | R244Drainage, sumps and moisture control | SEK 336,000 | 4% of structural scope as a buried-class screen | Class assumption — site investigation/RFQ required |
| Added | R245Integrated testing, commissioning and public-safe documentation | SEK 1,950,000 | 5% of MEP/protection/mission-system scope | Class assumption — commissioning plan required |
Active base WBS SEK 60,474,000 · owner/design and contingency are added in the scenario cards above · 12 removed rows across the archive remain visible as change history.
The three inputs most likely to move the current screen.
These deterministic stress cases simultaneously vary quantities, rates, scope allowances and contingency. They are not confidence intervals and no longer serve as the headline answer.
Links support a rate, scope boundary or method. Context-only sources are not represented as quotations.
Public ready-mix material check only; installed underground rates require RFQ.
Public retail material check only; cutting, bending, fixing, waste and underground logistics require RFQ.
Ordinary critical-facility sanity check, not protected-bunker equivalence.
Public sources establish specialized tested products but not project prices.
Protected county-administration command and coordination centre for severe peacetime crises, heightened readiness and war.
Facility built; reported as one of the first Swedish projects under the new Environmental Code.
B008Major modernisation completed.
B008Presented as a modern, operationally available facility used when specific emergency thresholds are met.
B004,B007 · B004 · B007Reported as actively used for peacetime training, videoconferences and meetings and available for crisis staffing.
B004,B007Publisher-reported features, not a current engineering inspection or certification.
Command room, planning/information/operations sections, co-operating agencies and Sveriges Radio studio.
B005Modern IT and telecoms, data/telecom room, public telephone-network connections, radio and media monitoring, and multiple carriers for resilience.
B006 · B013Two generating sets; independent of external electricity for a limited but unspecified period.
B006Air purification, outside-air cooling in peacetime and groundwater cooling during exercises/crises.
B006Own water for at least seven days.
B009Publisher calls it a substantial concrete bunker designed for severe stresses; no weapon rating is disclosed on the live page.
B003 · B00424 reviewed claims. Evidence locators resolve against the stored article hash or archived snapshot.
| Subject | Claim | Value | Date | Evidence | Certainty |
|---|---|---|---|---|---|
| milestone | Event | Facility built; reported as one of the first Swedish projects under the new Environmental Code. | 1998 | B008 | Reported |
| milestone | Event | Major modernisation completed. | 2014 | B008 | Reported |
| lifecycle summary | Event | Presented as a modern, operationally available facility used when specific emergency thresholds are met. | article date | B004,B007 | Reported |
| quantitative observation | Similar County Facilities Built In 1990s | 15 facilities | — | B008 | Reported |
| quantitative observation | Water Self Sufficiency | 7 days | — | B009 | Reported |
| quantitative observation | Nominal Staff | 60 persons | — | B009 | Reported |
| technical system | Command And Public Information | Command room, planning/information/operations sections, co-operating agencies and Sveriges Radio studio. | — | B005 | Reported |
| technical system | Communications | Modern IT and telecoms, data/telecom room, public telephone-network connections, radio and media monitoring, and multiple carriers for resilience. | — | B006,B013 | Reported |
| technical system | Power | Two generating sets; independent of external electricity for a limited but unspecified period. | — | B006 | Reported |
| technical system | Air And Cooling | Air purification, outside-air cooling in peacetime and groundwater cooling during exercises/crises. | — | B006 | Reported |
| technical system | Water | Own water for at least seven days. | — | B009 | Reported |
| protection | Buried Concrete Construction | Publisher calls it a substantial concrete bunker designed for severe stresses; no weapon rating is disclosed on the live page. | — | B003,B004 | Reported |
| lifecycle summary | Event | Reported as actively used for peacetime training, videoconferences and meetings and available for crisis staffing. | article era | B004,B007 | Reported |
| quantitative observation | Floor Area | 600 m² / 6,458 ft² | — | B003 | Reported |
| quantitative observation | Staff Capacity | 60 persons | — | B003 | Reported |
| quantitative observation | Roof Thickness | 2 m | — | B007 | Reported |
| quantitative observation | Wall Thickness | 2 m | — | B007 | Reported |
| quantitative observation | Generator Sets | 2 sets | — | B006 | Reported |
| quantitative observation | Implied Total From Unit Cost And Area | 30,000,000 SEK | — | B003 | Inferred |
| technical system | Command And Public Information | Command room, analysis, information, planning and operations sections, liaison spaces, videoconferencing and Sveriges Radio studio. | — | B004,B005 | Reported |
| technical system | Power | Two standby generating sets starting on grid failure and also supporting parts of other county-administration buildings. | — | B006 | Reported |
| technical system | Air And Cooling | Air cleaning; outside-air cooling normally and groundwater cooling during exercise/active operation. | — | B006 | Reported |
| technical system | Peacetime Use | Data training, videoconferencing, other education and meetings; data, PBX and IT equipment protected on site. | — | B007 | Reported |
| protection | Massive Concrete Shell | Roof and walls described as over two metres thick and capable of a direct hit; exact threat is expressly secret. | — | B007 | Reported |
Programme, sale, operating and component figures remain visible but are not silently relabelled as facility construction cost.
| Scope | Stage | Nominal | CPI 2025 | BKI 2025 | Date / evidence |
|---|---|---|---|---|---|
| reported construction unit cost {"amountBound":null,"amountQualifier":null,"unit":"SEK/m²","publisherEquivalentSek":null,"publisherEquivalentAsOf":null} | Other | SEK 50,000 | — | — | —B003 |