STRIL 60 command-data and radio architecture centred on FMR-10 transmitter facilities, with operational capacities, power, antennas and communications links.
No standardized area published
Start date not established
Published date and precision preserved
No unit-attributed image · 21 in the source article
Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware.
Provisional audited central concept screen; expected-risk calibration is pending. It is not yet a risk-adjusted expected cost.
Method, scope and confidence →Published, calculated and proxy dimensions are deliberately separated. Missing evidence stays visible instead of becoming zero.
Rock in place removed before bulking; the excavation-pricing quantity.
Internal airspace; not the amount of rock removed.
Blasted material after bulking; the haul and disposal quantity.
These cubic metres are not interchangeable.
Usable, floor or footprint area; the label is preserved because these are not always interchangeable.
No usable quantity in the reviewed source · Evidence gapRock in place removed before bulking; the quantity used to price excavation.
The audited morphology is not a rock-excavation class. · Audited morphologyInternal air or chamber volume. It is not solid excavation without overbreak, access and support geometry.
No usable quantity in the reviewed source · Evidence gapBlasted material after bulking, or its handled mass. No swollen cubic metres are inferred when only tonnes are modelled.
No rock mass-handling scope applies to the audited morphology. · Audited morphologyLength alone is insufficient; a costable tunnel also needs width, height or cross-sectional area.
No usable quantity in the reviewed source · Evidence gapPublished chamber or arch geometry used to test volume and support assumptions.
No usable quantity in the reviewed source · Evidence gapRock surface requiring bolts, mesh or shotcrete, preferably measured in square metres.
Rock-support surface does not apply to this audited morphology. · Audited morphologyCounts and dimensions of access, transfer, utility and emergency interfaces.
No usable quantity in the reviewed source · Evidence gapCast inner structures and linings, kept separate from excavated rock and reinforcement mass.
No usable quantity in the reviewed source · Evidence gapGroundwater, inflow, drainage, pumping and moisture-control evidence affecting construction and operation.
No usable quantity in the reviewed source · Evidence gapThe headline answers the current replacement question. Historic cost, CPI and construction-index comparisons remain separate because they answer different questions.
Different specifications receive different estimates; they are not used as the upper and lower limits of one answer.
Preserves documented capacity, protection, autonomy and redundancy using current construction methods.
Requires a modern structural, fire, protection and supplier performance brief.
Requires IT load, cooling topology, grid capacity, redundancy and autonomy. Server hardware is excluded.
No representative facility construction cost selected
General purchasing-power comparison—not a construction quote
Broad BKI proxy—not a bunker-specific rebuild price
Scope lock. Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware. The article is principally a STRIL/styrdata systems history. It supports procurement of 41 FMR-10 transmitters, a three-person wartime operating team per node, unmanned peacetime operation, seven equipment racks, antennas/transmission equipment and standby ge…
Audit revision sweden-replacement-audit-2026.08.15. The central WBS below incorporates the 61-article review. The former deterministic low/base/high cases remain available only as sensitivities and revision history.
Direct works + owner / design / investigation + legacy concept contingency
Central quantities × current installed-rate screen.
Not yet probability-weighted. The current legacy concept contingency remains separate.
22% applied to the direct-work screen.
Raw model SEK 3.28bn · rounded for Confidence E.
Transitional limitation. SEK 558,466,125 is still a blanket concept contingency, not probability-weighted expected risk. This is why the amount is labelled provisional. The audited telecom protected WBS remains the central scope ledger.
The archive record is a 41-site class/programme, not one physical bunker.
16/100 article-geometry completeness. Detailed source extraction is available in the original-article audit.
Confidence E · geometry completeness 16/100
Largest active lines in the audited central component schedule.
The workbook publishes one revised central schedule. Its prior low and high stress cases are retained only under sensitivities; no line-level probability distributions are implied.
No explicit active base-WBS line.
No explicit active base-WBS line.
Integrated testing, commissioning and public-safe documentation · SEK 106,374,500
| Change | Scope | Audited base | Quantity / rate basis | Provenance |
|---|---|---|---|---|
| Retained | 05Secure technical building or inner fit-outBuilding | SEK 175,890,000 | 5,330 m² / 57,372 ft² × SEK 33,000 / Usable m²Class Proxy quantity · Assumption rateProgramme total based on 41 sites at 80/130/180 usable m² per site; per-site sizes are explicit class proxies. | Existing archive WBS |
| Retained | 06Physical protection and resilienceProtection | SEK 106,600,000 | 5.92 Project × SEK 18,000,000 / ProjectAssumption quantity · Assumption rateOne protection package per 900 usable m² / 9,688 ft², subject to a 0.5-package minimum. | Existing archive WBS |
| Retained | 09Radio, transmission, power and cooling packageMission Systems | SEK 1,845,000,000 | 41 Site × SEK 45,000,000 / SiteDerived From Published quantity · Assumption rateThe estimate subject covers 41 sites. | Existing archive WBS |
| Added | R393Integrated testing, commissioning and public-safe documentation | SEK 106,374,500 | 5% of MEP/protection/mission-system scope | Class assumption — commissioning plan required |
Active base WBS SEK 2,233,864,500 · owner/design and contingency are added in the scenario cards above · 12 removed rows across the archive remain visible as change history.
The three inputs most likely to move the current screen.
These deterministic stress cases simultaneously vary quantities, rates, scope allowances and contingency. They are not confidence intervals and no longer serve as the headline answer.
Links support a rate, scope boundary or method. Context-only sources are not represented as quotations.
Public sources establish specialized tested products but not project prices.
The cited large-tunnel electrical award is a macro systems cross-check only; node package values are assumptions.
Transmit digital fighter-control commands and voice within STRIL 60.
First FMR-10 facilities were introduced.
B031LFC installations entered service with 12 radio relay/control positions each.
B010First RRGC entered operational service.
B012The wider system reached full build-out, including 28 additional positions.
B01215 reviewed claims. Evidence locators resolve against the stored article hash or archived snapshot.
| Subject | Claim | Value | Date | Evidence | Certainty |
|---|---|---|---|---|---|
| milestone | Event | First FMR-10 facilities were introduced. | late 1950s | B031 | Reported |
| milestone | Event | LFC installations entered service with 12 radio relay/control positions each. | mid-1960s | B010 | Reported |
| milestone | Event | First RRGC entered operational service. | 1966 | B012 | Reported |
| milestone | Event | The wider system reached full build-out, including 28 additional positions. | first half of 1970s | B012 | Reported |
| quantitative observation | Ps 08 Radar Sites | 4 sites | — | B008 | Reported |
| quantitative observation | Fmr 10 Transmitter Sites | 41 sites | — | B031 | Reported |
| quantitative observation | Wartime Site Crew | 3 persons | — | B032 | Reported |
| quantitative observation | Peace Transmitter Power | 150 W | — | B033 | Reported |
| quantitative observation | Wartime Transmitter Power | 10 kW | — | B033 | Reported |
| quantitative observation | Equipment Racks | 7 racks | — | B033 | Reported |
| technical system | Radio | Two antennas, VHF/FM and voice transmitters; source reports 108-155 MHz for FM and initially 108-160 MHz, later up to 399.95 MHz, for voice. | — | B033 | Reported |
| technical system | Communications | Wire and radio-relay links tied FMR-10 sites to command centres. | — | B033 | Reported |
| technical system | Power | Reserve generator supported wartime operation. | — | B033 | Reported |
| technical system | Planned UHF | A planned UHF addition was not realized. | — | B033 | Reported |
| protection | Distributed Architecture | Coastal two-row distribution reduced dependence on any one transmitter, but the article does not quantify structural hardening of FMR-10 buildings. | — | B031 | Reported |
No named project parties were extracted.