The archive documents Fält 8 Moholm as a buried-concrete wartime airfield later Bas 60. Construction is recorded from autumn 1939. Its documented role was dispersed wartime air operations.
No standardized area published
Published date and precision preserved
Completion date not established
Unit-attributed · 8 more or shared in the original article
Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware.
Provisional audited central concept screen; expected-risk calibration is pending. It is not yet a risk-adjusted expected cost.
Method, scope and confidence →47 photographs sourced from the original article, with captions where available.
Published, calculated and proxy dimensions are deliberately separated. Missing evidence stays visible instead of becoming zero.
Rock in place removed before bulking; the excavation-pricing quantity.
Internal airspace; not the amount of rock removed.
Blasted material after bulking; the haul and disposal quantity.
These cubic metres are not interchangeable.
Usable, floor or footprint area; the label is preserved because these are not always interchangeable.
No usable quantity in the reviewed source · Evidence gapRock in place removed before bulking; the quantity used to price excavation.
The audited morphology is not a rock-excavation class. · Audited morphologyInternal air or chamber volume. It is not solid excavation without overbreak, access and support geometry.
No usable quantity in the reviewed source · Evidence gapBlasted material after bulking, or its handled mass. No swollen cubic metres are inferred when only tonnes are modelled.
No rock mass-handling scope applies to the audited morphology. · Audited morphologyLength alone is insufficient; a costable tunnel also needs width, height or cross-sectional area.
No tunnel geometry applies to the audited morphology. · Audited morphologyPublished chamber or arch geometry used to test volume and support assumptions.
No usable quantity in the reviewed source · Evidence gapRock surface requiring bolts, mesh or shotcrete, preferably measured in square metres.
Rock-support surface does not apply to this audited morphology. · Audited morphologyCounts and dimensions of access, transfer, utility and emergency interfaces.
No usable quantity in the reviewed source · Evidence gapCast inner structures and linings, kept separate from excavated rock and reinforcement mass.
No usable quantity in the reviewed source · Evidence gapGroundwater, inflow, drainage, pumping and moisture-control evidence affecting construction and operation.
No usable quantity in the reviewed source · Evidence gapThe headline answers the current replacement question. Historic cost, CPI and construction-index comparisons remain separate because they answer different questions.
Different specifications receive different estimates; they are not used as the upper and lower limits of one answer.
Preserves documented capacity, protection, autonomy and redundancy using current construction methods.
Requires a modern structural, fire, protection and supplier performance brief.
Requires IT load, cooling topology, grid capacity, redundancy and autonomy. Server hardware is excluded.
No representative facility construction cost selected
General purchasing-power comparison—not a construction quote
Broad BKI proxy—not a bunker-specific rebuild price
Scope lock. Functional recreation of the documented facility in Sweden using current construction methods and 2026 prices, preserving the documented capacity, protection, autonomy and redundancy. Ex VAT; excluding land, financing, remediation, classified mission equipment and data-centre hardware. Whole-site history of two wartime fields about 2 km apart that merged into Fält 8/9 and were upgraded to Bas 60. Direct quantities include three 700 m runways at Fält 9, a later 2,000 m concrete runway, 38 initial revetments, 20 buried 100 m³ fuel tanks, 18 l…
Audit revision sweden-replacement-audit-2026.08.15. The central WBS below incorporates the 61-article review. The former deterministic low/base/high cases remain available only as sensitivities and revision history.
Direct works + owner / design / investigation + legacy concept contingency
Central quantities × current installed-rate screen.
Not yet probability-weighted. The current legacy concept contingency remains separate.
22% applied to the direct-work screen.
Raw model SEK 1.04bn · rounded for Confidence E.
Transitional limitation. SEK 177,156,250 is still a blanket concept contingency, not probability-weighted expected risk. This is why the amount is labelled provisional. The audited airbase system WBS remains the central scope ledger.
Inclusive whole-site estimate with a separately modelled KC child.
48/100 article-geometry completeness. Detailed source extraction is available in the original-article audit.
Confidence E · geometry completeness 48/100
Do not add this blindly to related records. Inclusive parent of se-falt-8-moholm-KC; never sum parent and child.
Largest active lines in the audited central component schedule.
The workbook publishes one revised central schedule. Its prior low and high stress cases are retained only under sensitivities; no line-level probability distributions are implied.
No explicit active base-WBS line.
No explicit active base-WBS line.
Integrated testing, commissioning and public-safe documentation · SEK 10,125,000
| Change | Scope | Audited base | Quantity / rate basis | Provenance |
|---|---|---|---|---|
| Retained | 05Support buildings and workshopsBuilding | SEK 231,000,000 | 7,000 m² / 75,347 ft² × SEK 33,000 / Usable m²Class Proxy quantity · Assumption rateProtected/support building-area proxy informed by two field hangars, 18 later positions, earlier shelters and the Bas 60 programme. | Existing archive WBS |
| Retained | 08Runway and dispersal pavementAirfield Civil | SEK 240,000,000 | 60,000 m² / 645,835 ft² × SEK 4,000 / Paved m²Assumption quantity · Assumption ratePublished concrete-runway length is 2000 m; 25/30/37.5 m width scenarios are explicit assumptions. | Existing archive WBS |
| Retained | 09Airbase command and mission systemsMission Systems | SEK 52,500,000 | 3.5 Reference Package × SEK 15,000,000 / Reference PackageAssumption quantity · Assumption rateOne mission package per 2000 usable m² / 21,528 ft², subject to a 1-package minimum. | Existing archive WBS |
| Retained | 10Dispersed fuel and protected supportProcess And Support | SEK 150,000,000 | 1 Airbase × SEK 150,000,000 / AirbaseAssumption quantity · Assumption rateThe estimate subject covers 1 site. | Existing archive WBS |
| Retained | 12External utilities and site integrationSite And Access | SEK 25,000,000 | 1 Site × SEK 25,000,000 / SiteAssumption quantity · Assumption rateThe estimate subject covers 1 site. | Existing archive WBS |
| Added | R399Integrated testing, commissioning and public-safe documentation | SEK 10,125,000 | 5% of MEP/protection/mission-system scope | Class assumption — commissioning plan required |
Active base WBS SEK 708,625,000 · owner/design and contingency are added in the scenario cards above · 12 removed rows across the archive remain visible as change history.
The three inputs most likely to move the current screen.
These deterministic stress cases simultaneously vary quantities, rates, scope allowances and contingency. They are not confidence intervals and no longer serve as the headline answer.
Links support a rate, scope boundary or method. Context-only sources are not represented as quotations.
Public material establishes specialized systems but no prices. Package values are assumptions and must not be read as classified equivalence.
Dispersed wartime air operations.
Land procurement began.
B010Construction began under contractor Kaspar Höglund.
B010Initial wartime-field phase.
B010,B013First aircraft arrival reported.
B010Fält 8 and Fält 9 were merged.
B013Merged and upgraded Bas 60 phase.
B013,B0372,000 m concrete runway completed as part of Bas 60 development.
B013Base downgraded.
B037Downgraded service, no Bas 90 conversion, followed by decommissioning and closure.
B037,B052,B054Military materiel decommissioning reported.
B054Base closed.
B05423 reviewed claims. Evidence locators resolve against the stored article hash or archived snapshot.
| Subject | Claim | Value | Date | Evidence | Certainty |
|---|---|---|---|---|---|
| milestone | Event | Land procurement began. | spring 1939 | B010 | Reported |
| milestone | Event | Construction began under contractor Kaspar Höglund. | autumn 1939 | B010 | Reported |
| milestone | Event | First aircraft arrival reported. | 1941-04-02 | B010 | Reported |
| milestone | Event | Fält 8 and Fält 9 were merged. | 1953 | B013 | Reported |
| milestone | Event | 2,000 m concrete runway completed as part of Bas 60 development. | 1956 | B013 | Reported |
| milestone | Event | Base downgraded. | 1968 | B037 | Reported |
| milestone | Event | Military materiel decommissioning reported. | 1993 | B054 | Reported |
| milestone | Event | Base closed. | 1999 | B054 | Reported |
| lifecycle summary | Event | Initial wartime-field phase. | 1939–1953 | B010,B013 | Reported |
| lifecycle summary | Event | Merged and upgraded Bas 60 phase. | 1953–1968 | B013,B037 | Reported |
| lifecycle summary | Event | Downgraded service, no Bas 90 conversion, followed by decommissioning and closure. | 1968–1999 | B037,B052,B054 | Reported |
| quantitative observation | Field 9 Runways | 3 runways | — | B010 | Reported |
| quantitative observation | Aircraft Revetments Initial | 38 positions | — | B010 | Reported |
| quantitative observation | Barn Shelters | 3 shelters | — | B010 | Reported |
| quantitative observation | Anti Aircraft Towers | 2 towers | — | B010 | Reported |
| quantitative observation | Concrete Runway Length | 2,000 m | — | B013 | Reported |
| quantitative observation | Underground Fuel Tanks | 20 tanks | — | B013 | Reported |
| quantitative observation | Later Aircraft Positions | 18 positions | — | B013 | Reported |
| quantitative observation | Field Hangars | 2 hangars | — | B013 | Reported |
| quantitative observation | Uom Distance From Base | 2 km | — | B013 | Reported |
| technical system | Fuel | Twenty underground 100 m³ fuel tanks. | — | B013 | Reported |
| technical system | Aircraft Dispersal | Revetments, field hangars, UOM and later aircraft positions supported dispersed operation. | — | B010,B013 | Reported |
| protection | Distributed Underground Fuel | Twenty separate underground tanks reduced concentration risk. | — | B013 | Reported |
Programme, sale, operating and component figures remain visible but are not silently relabelled as facility construction cost.
| Scope | Stage | Nominal | CPI 2025 | BKI 2025 | Date / evidence |
|---|---|---|---|---|---|
| Proposed civil conversion of Moholm airfield, compared with SEK 6m for Lidköping; not military bunker construction and apparently not executed. {"amountBound":null,"nonAdditive":true,"publisherLegacyEquivalentSek":null,"publisherLegacyEquivalentBasis":null} | Other | SEK 21,500,000 | — | — | mid-1980s contextB053 |